Supershield Limited v Siemens Building Technologies FE Limited

The Message In certain cases, a contract breaker will be liable for damage resulting from his breach, even if the damage would not have occurred in ordinary circumstances. The Case Supershield Limited v Siemens Building Technologies FE Limited concerned the allocation of responsibility for damage caused by a flood in a leading law firm’s offices. […]

20th Jan 2010 Recent Property Cases Read more

Westvilla Properties Limited v Dow Properties Limited

The Message The Court will strive to make a contract for the sale of land enforceable. The Case A purchaser sought to release itself from a contract on the basis that the documentation was incomplete and uncertain and was not binding upon it On 19 March 2008, Westvilla entered into a contract to sell to […]

15th Jan 2010 Recent Property Cases Read more